Watch

04

සි   |     |  

 Date: 2020-10-08   Answered 

0423/2020: Issues in constructing Kurunegala-Habarana Railway Line

423/2020

Hon. (Mrs.) Rohini Kumari Wijerathna,— To ask the Minister of Transport,—

(a) Will he explain to this House the present situation with regard to the construction of the Kurunegala-Habarana railway line?

(b) Is he aware that—

(i) three surveys have been carried out for the determination of the line of this project;

(ii) it has been decided to construct this railway line as per the third survey; and

(iii) the railway station proposed to be constructed close to Athuparayaya village, Dambulla as per third survey is located afar from the town than the land on which the proposed railway station was scheduled to be constructed in the first survey? 

(c) Will he inform this House—

(i) whether the land on which the proposed railway station is scheduled to be constructed close to Athuparayaya village as per the third survey is a land with very high economic value; and

(ii) if not, whether action will be taken to pay compensation in line with the current market value?

(d) If not, why?

 

Asked Date

2020-10-08

Asked by

Hon. (Mrs.) Rohini Kumari Wijerathna, M.P.

Ministry

Transport

Legislature

Ninth Parliament of the D.S.R. of Sri Lanka

Session

First Session

Question History

Answer

----

Answered Date

2020-10-08

Answered by

Hon. Johnston Fernando, M.P.